Curing requirements for concrete
Curing methods for concrete:
(1) Natural Maintenance (commonly used in on-site construction): covering and watering maintenance, film cloth maintenance, etc.
(2) Heat Treatment and Maintenance
2. Start of Natural Curing Time: Prior to final setting (usually 8-12 hours after pouring)
3. Concrete curing time requirements:
(1) Ordinary Portland Cement, Portland cement-silicate, slag Portland cement (heat-resistant, steam-cured): 7d
Volcanic ash (fly ash) slag cement concrete: 14d
(3) Concrete blended with retarding admixtures, mineral admixtures, or with requirements for impermeability: 14d
(4) Concrete with waterproofing (indoor, underground, seasonal, roof) and impermeability requirements: 14d
(5) Large volume concrete: 14d
(6) Post-tensioned concrete: 14d
(7) Waterproofing required for post-cast concrete: 28d