The construction steps for金刚砂toughened floor usually include:
Clean the floor to ensure it is clean and smooth.
2. Reinforce the ground with rebar to enhance its compressive strength.
3. Transport concrete and ensure it meets the required slump specifications.
4. Use a polishing machine to grind the floor and increase the mixture of concrete and diamond sand.
5. Sprinkle the silicon carbide evenly over the concrete floor and grind it with a polishing machine to ensure thorough bonding with the concrete.
6. After all grinding is complete, perform a secondary sanding and leveling.
7. Maintenance: Operation can be carried out after the floor surface has reached its final setting, generally by applying oil-based maintenance agents through spraying or brushing.
8. Cutting Seams: After maintenance is complete, perform cutting seam treatment to ensure the floor's flexibility.