Da Ze Power Diesel Generator ATS Automatic Transfer Switch Steps:
Upon power restoration, the system waits for 3-5 seconds before shutting down, and the generator turns off for 3-5 seconds before automatically switching to municipal power supply. Lack of this feature constitutes non-compliance.
After a total of 10 start-ups, the generator set will no longer start.
(3) In the event of an emergency shutdown during generator set operation, simply turn off the start key.
(4) In the event of a power outage, both manual and electric startup are available for the generator set. Once started successfully, the system will automatically switch to generator set power supply within 5-10 seconds.
(5) After a power outage, the battery's red wire maintains a DC voltage of 12-16V, with the red wire being positive (*).
(6) Upon power disconnection, the system can automatically start the generator set within 10-15 seconds.
Each startup takes 3-5 seconds.
(8) After the generator set stops starting, if it needs to be restarted, **turn the start key on and off once:**
(9) Generator fails to start when there is grid power available:
(10) If not successfully initiated, the system will automatically restart after a few seconds interval.