High-temperature resistant silicone coating for 500℃
Group Available BySiliconeResin, active rust-inhibiting pigments, penetrants, hardeners, and additives, etc.。
Sex Available This productNot only heat-resistant but also boasts excellent weathering and corrosion resistance. After high-temperature treatment, the coating links organic silicon and inorganic substances like silicate, thereby protecting the base material. This product improves the poor corrosion resistance of previous organic silicon coatings under normal temperatures, high temperatures, and alternating cold-hot water washing.
Please provide the Chinese content to be translated. Path Commonly used for temperatures ranging500Surface materials below 0°C serve decorative, protective, and anti-corrosion/rust functions. Such as fire bowls, barbecue grills, car exhaust pipes, etc.

Product Specifications
Temperature Range | Film Color | Coating Type | Mixture Ratio |
500℃ | Gray | Primer | Single-component, two-component |
500℃ | Black, white, gray, silver aluminum, etc. | Surfaces Paint | Single-component, two-component |
Technical Specifications
Project | Benchmark |
Color | Undercoat: Gray Surfaces Paint: Black, white, gray, aluminum powder, etc. |
Gloss | Undercoat: Matte Flat or Semi-Gloss Finish |
Viscosity | 25-60s(25±1°C, coated-4) |
Drying Time (23±2℃) | Undercoat: Surface dry≤1h, Hardworking ≤24h Surface Paint: Dry to the touch≤2h, Action ≤24h |
Flexibility | ≤2mm |
Adhesion | ≤2Grade |
Impact resistance | ≥40kg·cm |
Thermal resistance500℃,2h) | Non-bubbling and non-cracking |
Shelf Life | 25°C, Store away from light3-6month |
Construction Method
1. Raw Material Processing
Before painting operations, the base surface should be cleaned of oil stains, rust, foreign matter, etc. Sandblasting toSa2 grade, remove paint, rust, oxide scale, etc.
2. Mixed (for two-component paints)
Priced by weight ratio (as indicated on the product packaging)
Mix continuously while slowly adding the hardener to ensure thorough and even blending.
Pre-mixed Paint MaturationAfter 20 minutes, filter through a 60-80 mesh sieve and pour into another container for later use.
Mixed paint shelf life3 hours, please use according to the construction progress.
3. Baking (suitable for one-component paint)
Product Name | Baking Temperature | Insulation duration |
High-temperature resistant silicone coating with a melting point of 500℃ | 220℃ | 30min |
4. Construction Conditions
Spraying operations should be conducted as soon as possible after the substrate treatment, generally not exceeding8 hours. The substrate surface temperature and ambient temperature should generally not be below 10°C, with the surface temperature at least 3°C above the dew point, and the relative air humidity should not exceed 85%.
5. Coating Methods
This paint can be applied using brush painting, airless spraying, and air-assisted spraying methods.
6. Dilute
Generally, paints require a compatible thinner to adjust viscosity and clean tools.
7. Coating Spacing
One-component paint can be coated after drying. For two-component paint, it is recommended to wait the following time interval before coating:
Substrate Temperature | 5℃ | 20℃ | 30℃ |
Short | 48h | 24h | 12h |
Long | Unrestricted | ||