Suzhou Shunze Tong Electrical and Mechanical Installation Co., Ltd. was established in September 2013, located at No. 12 Datong Road, Suzhou High-Tech Industrial Development Zone. Our company specializes in the installation of various pipelines and equipment. In recent years, we have assisted the environmental protection industry in completing over two hundred pollution control projects, including wastewater and waste gas treatment, and soil remediation, earning high praise from our clients. We offer competitive steel structure installation costs and have entered into long-term cooperative agreements with our clients.
Steel structure installation
The installation of steel structures primarily utilizes welding, rivet bolts, and connections, so it is crucial to inspect the technical qualifications of welders, crane operators, and other specialized trades. Verify the qualifications and expiration dates of the issuing bodies for the steel structure installation company's operation safety certificates. Additionally, the project department establishes a quality assurance system, implements three inspection systems, and requires technical personnel to obtain certifications.

Methods for Steel Structure Installation
1. Steel structure installation begins with hoisting, typically starting from the center and then moving to the outer sides, following a bottom-up approach. First, secure the center section, then push from both ends. Once hoisted into place using tools, fasten with anchor bolts, and then weld the steel column bolts and clamping plates before installing the steel column.
2. Simultaneously, ensure the connecting rods between steel columns are properly installed to form a structural system, then proceed with assembly. Install the second row of steel columns, and then secure the connecting beams between the columns. Continue installing in this order, interweaving the steps, and install the trusses. Additionally, install joists, make connections, and then proceed with the roof panel installation, ensuring proper insulation material is laid. Only after meeting the water-resistant conditions can the steel structure guarantee insulation, heat preservation, and waterproofing effects.

Key Points for Steel Structure Installation
Pole Installation
To eliminate the impact of column length manufacturing errors on column elevation, before hoisting, measure 1m downward from the flat surface of the bracket as the theoretical elevation section. Quote for steel structure installation, mark it clearly as a reference for adjusting column elevation. The bottom surface of the column base is marked with diagonal lines crossing through the center of the column, serving as a reference for column installation alignment. During installation, the crossing lines on the column should overlap with the foundation. First, according to the marks on the theoretical elevation of the column, install the steel structure and use a level to correct the column elevation. Then, support the column with shims and tighten the anchor bolts. Next, use two theodolites to calibrate the verticality of the column from two axes, and tighten the bolts with double nuts after meeting the requirements. For columns that are single and unstable in structure, temporary protective measures can be taken using an air sling. For columns designed with inter-column supports, inter-column supports can be installed to enhance structural stability.

Steel Structure Installation - Shunzetong Electrical and Mechanical Installation Co., Ltd.1 - The steel structure installation quote is provided by Suzhou Shunzetong Electrical and Mechanical Installation Co., Ltd. The steel structure installation quote by Shunzetong Electrical and Mechanical Installation Co., Ltd.1 is a new upgrade launched this year. The above images are for reference only. Please call the contact number on this page or the image to request the contact person: Manager Ma.