High-speed mixing tank trial run:
1. Equipment should be installed on a level concrete foundation and secured with anchor bolts.
2. Pay attention to the vertical alignment of the main body with the level during installation.
3. After installation, check if all bolts are tight and if the main storage door is securely fastened. If loose, please tighten them.
4. Power up the high-speed mixing tank with appropriate power lines and control switches.
5. After inspection, conduct an empty load test run. If the test run is normal, production can proceed.