Based on the performance characteristics of natural stone powder coatings, the application of natural stone powder coatings is generally divided into the following three types of application techniques:
Example of Concrete Wall Coating with Natural Stone Powder
Layered approach example
1. Wall painting treatment
2. Wall repair with specialized base material
4. Leveling with natural stone powder coating by scraping or spreading
3. Leveling Base Material for Scraping (Smeared) Application
5. Scrape (Wipe) Natural Stone Powder Coating Surface

General Insulating Wall Coating Method with Natural Stone Powder
Layered approach examples
1. Wall painting treatment
2. Apply 2" thick thermal mortar
3. Wall Repair with Special Base Material
4. Leveling Base Material for Scraping (Applying)
5. Leveling with natural stone powder coating by scraping or spreading
6. Scrape (Wipe) Natural Stone Powder Coating Surface
General practice for natural stone powder coating on block walls
1. Apply a layer of glass fiber mesh at the wall junction
2. Wall Repair with Special Base Material
3. Leveling Base Material for Scrape (Spatula) Application
4. Leveling with natural stone powder coating by scraping (smearing)
5. Scrape (Wipe) Natural Stone Powder Coating Surface
Construction Caution Notices
1. Prior to the boundary painting work on walls, remove surface dust, grease, sealants, and debris from wall corners to ensure smooth construction.
Clean surface, apply anti-rust paint to metal items. For other walls, remove any protrusions exceeding the wall surface.5mm foreign object
Just ensure cleanliness; no special treatment required.
2. Professional Base Material Wall Repair: Utilize special base material for the mending of corners and straightening of convex and concave angles, with the concave angle being straightened using a right-angle ruler and...
The method for stringing lines: use an aluminum alloy straightedge with a right-angle ruler for the chamfered corners.
3. Level the base material by scraping, using a special base material and liquid in a 3:1 ratio to mix into a uniform paste. Scrape...
The surface must be level and perpendicular, with layers applied evenly.(Note: If the base error is significant, it can be leveled in multiple passes; each pass should not exceed ...)
10mm)。
4. Leveling coating surface with stone powder, mixed evenly with a ratio of 2:1 of natural stone powder to liquid.
Flat, with minimal scratches, standard scraping(Note: Intervals between coats should not be less than 2 hours, dry to the touch as the standard).
5. The stone powder coating surface should be polished with the same material ratio, requiring sandpaper to be used for smoothing before applying the first coat.
Construction is nearly completed to prevent dust and other pollutants. Requires two persons to work in coordination: one for scraping and spreading, the other for smoothing in the back.
Calendering. After drying, the surface is flat, smooth, and has a tactile feel. Clean the edges and corners, and ensure product protection.
Description: Detailed construction methods are subject to the final signed contract.
Note: The natural stone powder surface is divided into two types of powders (using troweling technique) and liquid (using spraying or rolling technique)
),Both products have the same raw material aggregates, developed for different usage purposes; the liquid product has powder
Products of the same physical properties.