Curing agent flooring construction is a common method of engineering construction, featuring its wear resistance, flatness, and aesthetic appeal. Below is an introduction to the complete curing agent flooring construction process:
Select the appropriate diamond blade model and install it. Firstly, we need to choose the suitable diamond blade model based on the different materials and hardness of the ground, and then install it on the grinder.
2. Conduct testing and polishing, inspect polishing scratches, and precisely locate the polishing depth. Before proceeding with formal polishing, it's necessary to first test the polishing to adjust the depth promptly and accurately identify the areas to be polished.
3. Clean the floor thoroughly, confirm the sanding plan, complete the tuning, and begin the horizontal, repetitive sanding process. After cleaning the floor, confirm the sanding plan, proceed with the tuning, and initiate the horizontal, repetitive sanding.
4. Load the dust from polishing into trucks for removal, and repair the expansion joints on the ground. Clean up the dust from polishing promptly and fix the ground's expansion joints to avoid affecting the later appearance.

5. Spread the curing agent material. Sprinkle the curing agent over the ground that has been ground, allowing the agent to penetrate the surface and react chemically with the cement, thereby increasing the ground's hardness.
6. Surface grinding with a grinder. After the curing agent material has been sprinkled, use a grinder to grind the surface of the floor.
7. Grind the resin grinding disc and mix the polishing solution. Next, use the resin grinding disc to sand the floor and mix an appropriate amount of polishing solution for even application.
8. Install the resin film, perform polishing, and this is the result. After applying the polishing liquid, install the resin film and carry out polishing to achieve a bright and attractive, wear-resistant, and smooth finish.
This is the complete process for the installation of the curing agent flooring. It is crucial to adhere strictly to the procedure during construction to ensure the quality and stability of the construction results. Additionally, safety precautions should be taken throughout the construction process to safeguard the health and safety of the workers.