Jiuhong Comprehensive Terminal -- Bulk Storage, General Cargo Yard Foundation Compaction Project: The Jiuhong Comprehensive Terminal of Jiujiang Port has a total length of 342 meters along the shoreline, located in the middle and lower reaches of the Yangtze River, adjacent to the northwestern shore of Poyang Lake, and situated to the east of the Gutang Chemical Fiber Textile Base, with a distinct geographical advantage. The project is designed with 2 general-purpose berths of 2,000 tons each and 1 chemical berth of 2,000 tons, with the hydraulic structures accommodating vessels up to 5,000 tons. The annual cargo throughput is 3.87 million tons, and the annual throughput capacity is 3.95 million tons. The foundation treatment compaction project uses low-energy compaction with a force of 2000KN.m and 1000KN.m.