Specification for Cementitious Grouting Materials - CGM Early Strength Grouting Material Manufacturer, In Stock

平台认证
  • Unit Price

    $860.00/ton

  • Brand

    Shi Jia Guo Jian

  • MOQ

    1ton

Contact
Leave Msg

Platform Service

Supplier Verified



广东士佳固建建材技术有限公司

VIP   数字营销第3年
资料通过中商114认证

Product Details

Specs

Gallery

  • Brand:

    Shi Jia Guo Jian

  • Unit Price:

    $860.00 / ton

  • MOQ:

    MOQ1ton

  • Total:

    10000ton

  • Address:

    GuangdongGuangzhou

  • Delivery:

    3days

  • View More

Description

Key Products: CGM High-Strength Non-Shrink Grouting Series, CGM-340, CGM-380, Epoxy Grouting, Epoxy Patching Mortar, CGM-320 Support Grouting, Quick-Fill Gravity Mortar, Support Mortar, CGM High-Strength Emergency Repair Material; High-Strength Polymer Mortar, Epoxy Support Grouting, Polymer Crack-Resistant Mortar, Polymer Waterproof Mortar, Cement Pavement Fast Repair Material, Rail Adhesive Mortar, Concrete Carbonation Prevention Coating, Bonding Agent, Prestressed Pipe Grouting Agent, Wear-Resistant Floor Hardener, etc., as well as product masterbatch...

CGM High-Strength Non-Shrink Grouting Material

Product Features: 1. Early and high strength: Compressive strength ≥27 MPa within 1 day; ≥40 MPa within 3 days; ≥60 MPa within 28 days.

2. Microexpansive

Ensure tight contact between the equipment and foundation, with no shrinkage after secondary grouting.

3. High self-leveling

Fills all voids, meets the requirements for secondary grouting of equipment.

4. Anti-settling

Overcame the phenomenon of segregation caused by excessive water addition during on-site use.

5. Crack-resistant

Cracking phenomena during on-site use due to uncertain water content, fluctuating environmental temperatures, and limitations on maintenance conditions.

6. High durability

After 500,000 fatigue tests and 50 freeze-thaw cycles, there is no significant change in strength. After soaking in engine oil for 30 days, the strength significantly improves.

7. Suitable for winter construction

Outdoor construction is permitted at temperatures as low as -10°C.

Product Application:

1. Used for secondary grouting of equipment foundations.

2. For anchoring ground bolts and reinforcing bar embedding.

3. Used for reinforcement and repair of concrete structures.

Technical Specifications:

Pre-construction preparations

1. Machine Mixing: Concrete mixer or mortar mixer;

2. Manual Stirring: Several mixing tanks and shovels.

3. A number of buckets.

4. Several scales

5. Chute

6. High-position funnels, grouting pipes, and pipe fittings;

7. Grouting Propeller

8. Templates (steel molds, wood molds)

9. Sacking bags, mineral wool blankets, etc.

10. Cotton yarn, tape

Grouting construction

Step 1: Basic Processing

The base surface should be roughened. Clean the base surface, free from debris such as gravel, slurry, loose dust, oil stains, and release agents. Prior to grouting, the base surface should be thoroughly moistened 24 hours in advance, and standing water should be cleared 1 hour before grouting.

Step 2: Feel and inspect

1. Set up forms according to the grouting construction drawing. Seal the joints between the forms and the foundation, as well as between forms, using cement grout and tape to ensure the entire form set is watertight.

2. The horizontal distance around the template and equipment base should be maintained at about 100mm to facilitate grouting work.

3. The template top elevation should be 50mm higher than the surface of the equipment base.

4. If there is any leakage during the grouting process, it should be addressed promptly.

Step 3: Grout Material Preparation

Generally, water is mixed at a standard of 13-14% for general reinforced type, and 9-10% for pebble reinforced type.

2. Use mechanical stirring method; stirring time is generally 1-2 minutes (drills with electric drill-style stirrers are strictly prohibited). When stirring manually, first mix with 2/3 of the water for 2 minutes, then add the remaining water and stir until uniform.

3. The mixing quantity should be determined based on the usage amount to ensure the material is used up within 40 minutes.

4. Under no circumstances should any admixture or external additive be mixed with CGM grouting material during on-site use.

Step 4: Grouting Construction Method

1. For longer equipment or track foundations, segmented construction should be employed.

2. Illustrations of Common Grouting Methods

3. During the secondary grouting, the following requirements should be met.

1.1 During secondary grouting, the grout should be applied from multiple points on one side or adjacent sides until it overflows from the opposite side, to facilitate air release during the grouting process. Grouting from all four sides simultaneously is not allowed.

1.2 Once grouting begins, it must be conducted continuously without interruption, and efforts should be made to minimize the grouting time.

1.3 It is strictly forbidden to vibrate during the grouting process. If necessary, use a grouting booster to push the CGM grouting material along the bottom of the grouting layer, strictly prohibiting pushing from the middle or upper part of the grouting layer to ensure the homogeneity of the grouting layer.

After the equipment foundation grouting is completed, a 45-degree bevel should be cut along the edge of the equipment within 3-6 hours post-grouting (refer to the illustration below) to prevent cracks from forming at the ends. If edge trimming is not possible, the grouting layer surface should be smoothed with a trowel within 3-6 hours after grouting.

When the thickness of the grouting layer exceeds 150mm, it is recommended to use reinforced coarse aggregate high-strength shrinkage-free grouting material.

1.6 When the amount of equipment base grouting is large, mechanical mixing should be used for the stone reinforcement grouting material to ensure the grouting construction.

Step 5: Maintenance

1. Immediately cover with a wet straw mat or rock wool blanket within 30 minutes after grouting, and maintain its moisture.

2. During winter construction, the maintenance measures should also comply with the relevant provisions of the current (GB50204).

3. After the grouting material reaches the demolding time, the equipment installation can be carried out. Please refer to the "Demolding and Curing Time vs. Environmental Temperature Chart" for the specific time.

4. After the equipment foundation grouting is completed, if any parts need to be removed, they can be gently scraped off with a trowel or shovel tool 3-6 hours after grouting, before the grout hardens.

5. Do not transmit vibration from operating machinery to the equipment foundation. After secondary grouting, the machine should be shut down for 24-36 hours to prevent damage to the unhardened grout layer.

Packaging and Storage

Packaging specification: 50kg per bag, store in a well-ventilated and dry place, and protect from direct sunlight.

Guangxi: Liuzhou, Nanning, Qinzhou, Laibin, Guigang, Chongzuo, Yulin, Guilin, Wuzhou, Baise, Hezhou, Beihai, Hechi, Fangchenggang

Guangdong: Shenzhen, Guangzhou, Shaoguan, Jiangmen, Yunfu, Yangjiang, Zhuhai, Qingyuan, Maoming, Shantou, Foshan, Zhongshan, Huizhou, Meizhou, Dongguan, Zhaoqing, Zhanjiang, Heyuan, Shanwei, Chaozhou, Jieyang

Guangzhou Yuexiu District, Tianhe District, Baiyun District, Liwan District, Luogang District, Huangpu District, Haizhu District, Panyu District, Huadu District, Nansha District, Zengcheng City, Conghua City

Shenzhen, Luohu District, Futian District, Nanshan District, Bao'an District, Longgang District, Guangming New District, Pingshan New District, Yantian District

Zhuhai, Doumen District, Jinwan District, Xiangzhou District

Shantou, Chao'an District, Chaoyang District, Chenghai District, Haizhu District, Jinping District, Longhu District, Nanao District

Foshan, Chancheng District, Nansha District, Shunde District, Sanshui District, Gaoming District

Shaoguan, Lechang, Nanyong, Qujiang District, Renhua, Ruyuan, Xisheng, Wengyuan, Wujiang District, Xineng, Xianjiang District

Zhanjiang, Chikan District, Leizhou, Lianjiang, Mazhang District, Potou District, Suixi, Wu'chuan, Xushan, Xuwen

Zhaoqing, Deqing, Dinghu District, Duanzhou District, Fengkai, Gaoyao, Guangning, Huaiji, Sihui

Jiangmen, Enping, Heshan, Jianghai District, Kaiping, Pongjiang District, Taishan, Xinhui District

Maoming, Maoming Port Area, Huazhou, Xinyi, Gaoyou, Dianbai

Huizhou, Huicheng District, Huizhou District, Huizhou East, Boluo, Longmen

Meizhou, Dabu, Fengshun, Jialing, Meijiang District, Meixian, Pingyuan, Wuhua, Xingning

Shantou City, Haifeng, Lufeng, Luhe

Heyuan, Dongyuan, Pinghe, Lianning, Longchuan, Yuancheng, Zijin

Yangjiang, Jiangcheng District, Yangchun, Yangdong, Yangxi

Qingyuan, Fugang, Liannan, Lianshan, Lianzhou, Qingcheng District, Qingxin, Yangshan, Yingde

Dongguan, Duanzhou District, Fengkai, Gaoyao, Guangning, Huaiji, Sihui, Doumen District

Zhongshan, Chaozhou, Chao'an, Raoping, Xiangqiao District

Jieyang, Huilai, Jiedong, Jiexi, Puning, Rongcheng District

Yunfu, Luoding, Xinxing, Yunan, Yun'an, Yuncheng District

Haikou, Longhua District, Meilan District, Qiongshan District, Xiuying District

Sanya State-owned Farm, Hainan Bay Town, Jiyang Town, Fenghuang Town, Hexi District, Hedong District, Yacheng Town, Tianya Town, Yucai Town

Sansha City, Wuzhishan City, Qionghai, Danzhou, Wenchang, Wanping, Dongfang, Chengmai, Ding'an, Tunchang, Lingao

Baisha, Changjiang, Ledong, Lingshui, Baoting, Qiongzhong






Disclaimer:Info provided by user, user liable for authenticity, accuracy & legality. Zhongshang114 assumes no liability.

Tip:Confirm supplier qualification & quality before purchase to avoid risks.

Unit Price $860.00 / ton
Sales None
Delivery GuangdongGuangzhou3dayswithin
Stock 10000tonMOQ1ton
Brand Shi Jia Guo Jian
Compressive Strength C60MPa
Origin Guangzhou
Item Number 42.5R
Expiry Long Valid
Update 2023-05-11 11:38
Gallery

Guangdong Shijia Gujian Building Materials Technology Co., Ltd.Published bySpecification for Cementitious Grouting Materials - CGM Early Strength Grouting Material Manufacturer, In StockGallery Lib

Contact Merchant



Join

Successful Enterprise Join, Enjoy Multiple Privileges

Join Hotline:4006299930

Please scan with mobile phone

Customer Service

Service Hotline:4006299930

Official Account

WeChat Official Account, Get Business Opportunities

Scan to follow WeChat

Top