Lead shielding doors, lead skins, lead rooms, lead plates...

Prior to the completion of the overall installation of the air conditioner factory structure, support or wind rope anchoring treatments must be employed during the installation process to prevent lateral overturning. Construction Techniques: Pre-fabricated protective wall; Component manufacturing.
1) All steel sections must be straightened before cutting, regardless of whether they are joined or not, based on the actual condition of the incoming materials.
2) The node board is laid out and checked for cutting dimensions before being processed. During numbering, allowances are made for cutting based on actual conditions.
Processing Allowance
3) Purlins must be at least 1 meter in length, with each rod having fewer than two joints, and the joint locations must be away from the weld seams at the node edges.
The distance is not less than 500mm, and the rod joints should avoid the bolt hole positions.
4) After the components are cut to size, bolt hole processing is immediately carried out according to the diagrammed locations; all bolt hole positions must be considered.Lead SheetConnecting
Installation and location.
b) Assembled in Sheets or Frames
1) Erect pillars on the tubular platform, adjust the spacing, horizontal and diagonal dimensions to meet specifications, and then weld and secure the barriers.
Quick;
2) First, install the upper and lower connecting beams, followed by the other connecting structures in sequence.
3) After the welding of each single piece's connection structure is completed, inspect the外形尺寸, horizontal level, diagonal, and other dimensions of the single piece structure.
4) Assemble two pieces into a frame on the platform, following the same method and requirements as above. After checking and confirming, proceed with the top and side...
Surface Welded Lugs
5) Assemble and install the cut or processed composite lead plates onto the steel frame structure using bolts on the platform.
Wall Protection Installation
1) Inspect and verify whether the ground treatment meets the requirements, and the installation axis ground levelness of the protective wall should generally not exceed...
In cases where the 10mm requirement is not met, a leveling treatment using steel plates should be conducted before or during installation.
2) Panels or framed walls will be transported to the installation site, with necessary precautions taken during hoisting and transportation.
Our protective measures prevent the deformation of the protective wall.
3) During on-site hoisting, start from one side, and immediately align and secure the panels or frames after hoisting, proceeding in this order of connection.
Install the security firewall.
The support structure for the protective wall should be installed concurrently with the protective wall, ensuring uniform load distribution and stable installation.
5) Inspect the firewall immediately after installation to confirm that the bolts are tightened, welds are secure, and ground mounts are in place.
If not meeting the requirements, the bolt tightening and welding specifications should refer to the relevant construction acceptance specifications for steel structures.