    YT Inorganic Active Material

    2024-10-28

    I. Pre-construction Preparation

    The base wall has passed the engineering inspection and meets the quality standards. Prior to construction, dust and debris on the base surface should be removed.

    Dirt and grease are thoroughly cleaned.

    II. Construction Key Points

    YT inorganic active thermal insulation material is applied in a 1:1.2 weight ratio of product to water.

    Place the mixer to thoroughly blend and stir, controlling the time to2-4 minutes, viscosity adjusted for easy application

    Operation by workers. Three, construction steps.

    First, clean the dust and grease from the base wall surfaces with clean water and achieve moderate wetness, then mix

    No content provided.YT thermal insulation material is directly applied onto the base wall or onto the cement mortar surface that has already been constructed.

    Thickness:10mm and under, apply force evenly and compactly; when the moisture content of the material is reduced to 50%.

    At the appropriate time, perform a batch application, ensuring the thickness is controlled.10-20mm.

    YT Insulation Materials can be applied in a single coat up to a thickness of 20mm, and up to 30mm in thickness.

    Second batch application completed.

    YT thermal insulation material has an initial setting time of approximately 3 hours, with all processes completed in a single day. It can be bonded after 10 days.

    Face tile installation15 days for coating finish. If the base wall is a concrete shear wall, it requires advance preparation.

    Sky Interface Mortar Treatment (Roughening), gaps between different wall materials require mesh reinforcement (glass).

    Fiberglass or galvanized steel wire mesh is used to alleviate the stress variations caused by different thermal expansion and contraction coefficients of the basic wall materials.

    Impact on Insulation.

    When adhesive bricks are required on the exterior of an insulation layer, the surface of the insulation layer needs to be roughened. Typically, this can be done with a wooden trowel.

    Childen's mitten texture, or create insulating surface grooves; for those with an insulating layer coated with paint, the surface of the insulating layer can be used

    Iron trowel smoothing treatment.

    Insulation surface bubbles due to compression during construction are a normal occurrence; simply puncture, flatten, and smooth them out.




Contact us

Hebei Yintong Building Materials Co., Ltd.
Service Hotline 13784882088
Company Phone 13784882088
Company Address Hebei Wuqiang County, Hengshui

Message Consultation

 Click OK to indicate that you agree to《Service terms》《Privacy policy》

b2b.china9.net © Zhongshang 114 Hebei Network Technology Co., Ltd.Address: Room 6009, Oriental New World Center, No.118 East Zhongshan Road, Qiaoxi District, Shijiazhuang City, Hebei ProvincePlatform Service Hotline: 4006299930

 Click OK to indicate that you agree to《Service terms》《Privacy policy》