Preparation for Construction
The base wall has passed the engineering inspection and meets the quality standards; prior to construction, dust on the base surface should be cleaned.
Clean dirt and oil stains thoroughly.
II. Construction Key Points
YT inorganic active thermal insulation material is applied during construction in a weight ratio of 1:1.2 between the product and water.
Mix the contents in the blender thoroughly for 2-4 minutes, adjusting the consistency to a workable level.
Operations are straightforward. Three, construction steps.
First, clean the dust and grease from the base walls with clean water and ensure moderate moisture, then mix
Good YT thermal insulation material is directly applied onto the base wall or on the already constructed cement mortar surface.
Thickness below 10mm, apply force, evenly, and compact; when the moisture content of the material is reduced to 50%.
At this stage, it can be applied in batches, with the thickness of each batch being controlled between 10-20mm.
YT thermal insulation materials can be applied in a single coat up to 20mm thick, and up to 30mm thick.
Second batch application completed.
YT thermal insulation material has an initial setting time of about 3 hours, with all processes completed on the same day, and can be bonded after 10 days.
Glue tiles, and the surface can be painted after 15 days. If the base wall is a concrete shear wall, it needs to be pre-
Day-to-day surface mortar treatment (skimming), gaps between different wall materials should be treated with a wire mesh (glass fiber mesh).
Fiberglass or galvanized wire mesh is utilized to alleviate the stress changes caused by the different thermal expansion and contraction coefficients of the base wall materials.
Impact on Insulation.
When adhesive bricks are needed on the exterior of an insulating layer, the surface of the insulating layer should be roughened, usually with a wooden trowel.
Child's play to add a plush texture or insulating surface grooves; for those with a painted finish on the insulating layer, the surface of the insulating layer can be used.
Trowel smoothing finish.
Insulation surface bubbling during construction is a normal occurrence; simply puncture, compress, and smooth it out. Notes:
1. YT Insulation Materials: Upon arrival, proper stacking is crucial to prevent moisture and rain. Any material that has formed lumps is strictly prohibited.
Utilize
2. YT Insulation Materials is a single-component material, ready to use by simply adding water and stirring. Absolutely no additional materials are permitted.
Material
3. YT thermal insulation material, mixed with water and ready for use, is typically consumed within about three hours.
Do not remix after the next day or after it dries.
4. For the base materials of autoclaved aerated concrete, clay bricks, and cellular bricks, they should be moistened with water before applying the plaster.
YT Insulation Materials
5. For concrete structures at the grassroots level, the surface must be treated with a casting and roughening process, followed by a subsequent coat the next day.
Apply YT thermal insulation material; surface treatment with spattered slurry is also required for building beams and columns.
6. Before construction, it is necessary to make gray cakes, notches, reinforcing or hanging line treatments on the wall. Discover the concavity of the base surface.
If there is an error greater than 1.5 centimeters, level it with cement mortar, roughen it up before proceeding with the construction.
To ensure optimal adhesion between the thermal insulation material and the substrate, the application must be firmly compacted throughout.
Thickness should be controlled at around 10mm. Apply the material again when the moisture content of the first application drops by about 50%, and continue until the desired thickness is achieved. When doing the tile facing, use a tool to compact and roughen the surface. For the applied facing,
During the smoothing process, finishing is performed. Note: It is difficult to level with a trowel when the moisture content is high; it needs to be waited for the moisture to evaporate.
When the layer has fallen by 30%, use a scraper to level it to prevent delamination.
8. YT Insulation Material Climate Requirements: Air temperature should not be below 5°C during winter, and sunshine should be avoided during summer.
Direct sunlight, temperature over 25°C requires watering maintenance. No construction during winds of 5 or more levels and rainy weather.
9. When applying thermal insulation adhesive bricks, if mesh fabric is used, it must be paired with anti-crack mortar, strictly.
Prohibiting the direct application of tiles after completing the mesh, as the bond between the tile adhesive and the mesh is not very strong, which is prone to causing porcelain tiles to crack.
Brick hollowing and falling off.
10. During the application of YT thermal insulation materials, minimize back-and-forth rubbing and instead, directly apply pressure to achieve better results.
11. Ensure product protection: For freshly finished walls, avoid rain soaking and collisions to maintain the integrity of the work.
The construction site is well-ventilated and dry. It is essential to clean the construction tools and mixers promptly after each job to prevent any impact.