Shandong Yantai Integrated Pre-fabricated Pump Station
The arrangement shall comply with the provisions of the "Code for Structural Design of Structures for Water Supply and Drainage Engineering" GB50069, and shall also meet the following requirements:
1 Comply with the requirements for the layout, installation, operation, and maintenance of mechanical and electrical equipment.
2 Meets structural layout requirements;
3 Meets requirements for ventilation, heating, lighting, and is compliant with technical specifications for moisture-proofing, fire prevention, noise reduction, energy conservation, labor safety, and industrial hygiene.
4 Meets transportation requirements.
Achieve an aesthetically pleasing arrangement that harmonizes with the surrounding environment.
Section 3: The elevation of the bottom plate of the integrated sewage lifting pump station should be determined in accordance with the installation elevation of the pump, the layout of the inlet channel or pipeline installation requirements, and should also consider the topographical and geological conditions of the pre-fabricated pump station.
Four, auxiliary equipment, electrical equipment, pipelines, and cable trays installed around the pump station's wastewater lifting pumps should be arranged to avoid cross-interference.
Five, the noise generated during the operation of the sewage lifting station shall comply with the provisions of the current national standard "Design Code for Noise Control in Industrial Enterprises" GB/T50087.
Six. The fire resistance grade of the sewage lift station should be lower than Grade II. Fire protection facilities should be installed near the prefabricated pump station, and they should comply with the current national standards for architectural fire prevention, GB 50016, and the current national standards for fire prevention design of hydraulic and water conservancy projects, SL 329.
Section 7: The design of the sewage lifting station shall comply with the provisions of "Design Code for Pumping Stations" GB50265.






Shandong Yantai Integrated Pre-fabricated Pump Station