    Pre-installation inspection before pressure testing the bellows compensator system

    2025-05-25

    Pre-installation inspection before pressure testing the bellows compensator system

    Thoroughly inspect the entire piping system, with particular attention to the following points:

    (1) Are the fixed brackets, guide brackets, and bracket installations in accordance with the system diagram?

    (2) Was the appropriate bellows compensator correctly installed in the designated location?

    (3) Are the pre-displacement and flow direction of the expansion joint correct?

    (4) Has the expansion joint's transportation restraint device been fully dismantled in accordance with regulations (except for special requirements)?

    (5) If the system is designed for gas flow medium, and water is to be used for pressure testing, should...

    Proper support is provided for the additional static load due to water weight on the pipelines and expansion joints; when the pipeline

    During segmented testing, has the manufacturer confirmed: Are the necessary temporary supports and fastening devices properly installed?

    (6) Are all guide brackets, pipe brackets, and bellows compensators designed to allow free movement of the pipe?

    Are the expansion joints all intact and undamaged?

    (8) Are there any misaligned expansion joints along the central axis? To verify this, measure the total length of the expansion joints.

    Inspect the geometric shape of the ripple and check the spacing between the critical points on the expansion joint and other critical points on the system.

    Are there any foreign objects trapped within the bellows and other movable parts of the expansion joint?

    8.3 System Pressure Testing During and After Pressure Testing

    During the system pressure testing (extreme caution must be exercised to ensure safety) and upon completion of the testing, the system should be externally inspected.

    Observation and inspection, with the following items checked:

    (1) Are there any signs of leakage or pressure loss.

    (2) Fixed brackets, bellows compensator components, especially those structural components that bear pressure thrust, bellows tubes, and

    Are there any abnormal deformations or yieldings in other pipe fittings?

    Under pressure, does the pipeline exhibit unexpected displacement?

    (4) Signs of instability (buckling) in the bellows.

    (5) Are there any obstructions in the movement of the guide brackets, bellows compensators, and other moving parts of the system?

    Indications.



Contact us

Jiangsu Yaguang Corrugated Pipe Co., Ltd.
Service Hotline 15380322300
Company Phone 15380322300
Company Address Jiangsu Province, Taizhou City, Jiangyan District, Louzhuang Town, Louzhuang Village

Message Consultation

 Click OK to indicate that you agree to《Service terms》《Privacy policy》

b2b.china9.net © Zhongshang 114 Hebei Network Technology Co., Ltd.Address: Room 6009, Oriental New World Center, No.118 East Zhongshan Road, Qiaoxi District, Shijiazhuang City, Hebei ProvincePlatform Service Hotline: 4006299930

 Click OK to indicate that you agree to《Service terms》《Privacy policy》