Factory Steel Structure Column Base Anchor Grouting Material, Factory Direct High-Strength Casting Material_SupplyPro Co., Ltd._Guangdong Shijia Gaojian Building Materials Technology Co., Ltd. 
在线客服 在线客服邀请中...
关闭

您好,现在客服正邀请与您通话,请留下您的联系方式,客服将尽快与您取得联系。

 点击提交代表您同意《服务条款》《隐私政策》
Guangdong Shijia Gaojian Building Materials Technology Co., Ltd.

High-strength non-shrink grouting material, high-strength polymer mortar, bea...

Consultation Hotline
13829788227

News Center Co., Ltd.

Product Categories
Home > SupplyPro Co., Ltd. > Factory Steel Structure Column Base Anchor Grouting Material, Factory Direct High-Strength Casting Material
Factory Steel Structure Column Base Anchor Grouting Material, Factory Direct High-Strength Casting Material
品牌: Shi Jia Guojian
Product Features:
Material: Cementitious Grouting Material
Origin: Guangdong
单价: 990.00/ton
最小起订Quantity: 1 ton
供货总Quantity: 10000 ton
有效期至: 长期有效
最后更新: 2022-12-26 14:58
 
详细Info

Shenzhen Steel Structure Base Installation Grouting Material Manufacturer, Zhuhai Steel Structure Anchor Grouting Material Manufacturer, Huizhou High Strength Non-Shrinkage Grouting Material Manufacturer, Dongguan Support Base Installation Grouting Material Manufacturer, Guangzhou Equipment Foundation Installation Grouting Material Manufacturer.

Main Products:CGM High-Strength Non-Shrink Grouting Series, CGM-340, CGM-380, Epoxy Grouting, Epoxy Patching Mortar, CGM-320 Support Grouting, Fast-Fill Gravity Mortar, Seat Mortar, CGM High-Strength Emergency Repair Material; High-Strength Polymer Mortar, Epoxy Support Grouting, Polymer Crack-Resistant Mortar, Polymer Waterproof Mortar, Rapid Repair Material for Cement Pavement, Track Mortar, Concrete Carbonation-Resistant Coating, Surface Treatment Agent, Prestressed Pipe Grouting Agent, Abrasion-Resistant Floor Hardener, etc., as well as product masterbatch...

CGM High-Strength Non-Shrink Grouting Material

Product Features1. Early strength, with compressive strength of ≥27 MPa in 1 day; ≥40 MPa in 3 days; and ≥60 MPa in 28 days.

2. Microexpansivity

Ensure tight contact between the equipment and foundation, with no shrinkage after secondary grouting.

3. High fluidity

Fills all voids, meets the requirements for secondary grouting of equipment.

4. Anti-segregation

Overcame the phenomenon of segregation caused by excessive water addition during on-site use.

5. Crack Resistance

Cracking phenomena during on-site use due to uncertain water addition, ambient temperature, and limited maintenance conditions.

6. Strong durability

After millions of fatigue testsNo significant change in strength after 50 freeze-thaw cycles. Strength notably improved after 30 days of soaking in engine oil.

7. Suitable for winter construction

Permitted toOutdoor construction at -10℃ temperatures.

Product Application:

1. Used for secondary grouting of equipment foundations.

2. For anchoring foot bolts and embedding rebar.

3. Used for reinforcing and repairing concrete structures.

Technical Specifications:

Pre-construction preparation

1. Mechanical Mixing: Concrete or Mortar Mixers

2. Manual Stirring: Several mixing tanks and shovels

3. Several buckets.

4. Several scales

5. Flow Channels

6. High-position funnels, grouting pipes, and pipe joints

7. Grouting Propeller

8. Templates (steel molds, wood molds)

9. Burlap bags, rock wool blankets, etc.

10. Cotton yarn, tape;

Grouting construction

Step 1: Basic Processing

The base surface should be roughened. Clean the base surface, ensuring there is no debris, slurry, loose dust, oil stains, or release agents. Prior to grouting.24 hours, the base surface should be fully moistened. One hour before grouting, remove any standing water.

Two-step: Feel

1. Set up forms according to the grouting construction drawing. Seal the joints between the forms and the foundation, as well as between forms, using cement grout and tape to ensure the entire form set is watertight.

2. The horizontal distance around the template and base should be maintained at about 100mm to facilitate grouting work.

3. The template's top elevation should be 50mm above the surface of the equipment base.

4. If leakage occurs during grouting, it should be addressed promptly.

Step 3: Grout Material Preparation

Generally, water is mixed in accordance with a standard of 13-14% for general reinforced type, and 9-10% for stone aggregate reinforced type.

2. Use mechanical stirring, which typically takes 1-2 minutes (do not use a drill-type stirrer). When stirring manually, first mix for 2 minutes with 2/3 of the water, then add the remaining water and stir until uniform.

3. The mixing quantity should be determined based on the usage amount to ensure the material is used up within 40 minutes.

4. During on-site use, it is strictly prohibited to mix any admixtures or external additives into CGM grouting material.

Step 4: Grouting Construction Method

1. For longer equipment or track foundations, segmented construction should be employed.

2. Diagrams of several commonly used grouting methods

3. During secondary grouting, the following requirements should be met.

1.1 During the secondary grouting, the grouting should be performed from multiple points on one side or adjacent sides until it overflows from the opposite side, to facilitate air release during the grouting process. Grouting from all four sides simultaneously is not allowed.

1.2 Once grouting begins, it must be carried out continuously without interruption, and efforts should be made to minimize the grouting time.

During grouting, vibration is strictly prohibited. If necessary, the CGM grouting material can be propelled along the bottom of the grouting layer using a grouting propeller; it is strictly forbidden to push from the middle or upper part of the grouting layer to ensure the homogeneity of the grouting layer.

1.4 After the equipment foundation grouting is completed, a 45-degree bevel should be cut along the equipment edge within 3-6 hours post-grouting (as shown in the figure below) to prevent cracks from forming at the ends. If edge cutting is not possible, the grouting layer surface should be smoothed with a trowel within 3-6 hours after grouting.

When the thickness of the grouting layer exceeds 150mm, use reinforced aggregate high-strength shrinkage-free grouting material.

1.6 When the base grouting volume of the equipment is large, mechanical mixing should be used for the aggregate reinforced grouting material to ensure the grouting construction.

Step 5: Maintenance

Within 30 minutes after grouting is complete, immediately cover with wet straw or mineral wool blankets and maintain moisture.

2. During winter construction, maintenance measures should also comply with the relevant provisions of the current (GB50204).

3. After the grouting material reaches the time for peeling off the film, installation of the equipment can be carried out. Refer to the "Table of Relationship Between Film Peeling and Curing Time and Environmental Temperature" for the specific time.

4. After the equipment foundation grouting is completed, if any parts need to be removed, they can be gently scraped off with a trowel or shovel tool 3-6 hours after grouting, before the grout hardens.

5. Do not transmit vibration from operating machinery to the equipment foundation. After secondary grouting, the machine should be shut down for 24-36 hours to prevent damage to the unhardened grouting layer.

Packaging and Storage

Packaging specification: 50kg/bag, store in a well-ventilated and dry place, and protect from direct sunlight.

Guangxi: Liuzhou Nanning Qinzhou Guests Guangxi Zhuang Autonomous Region, Guangzhou Port Chongzuo Yulin Guilin Wuzhou Baise Hezhou Beihai Hechi Fangchenggang Port

Guangdong: Shenzhen Guangzhou Shaozhou Jiangmen Yunfu Yangjiang Zhuhai Qingyuan Maoming Shantou Foshan Zhongshan Huizhou Meizhou Dongguan Zhaoqing Zhanjiang Heyuan Shantou Chaozhou Jieyang

询价单
主题 *
内容 *
Your company's名
Contact person *
ContactPhone *
电子Email
验证码  
 点击确定代表您同意《服务条款》《隐私政策》
 
 Click submit means you agree to《Service terms》《Privacy policy》

13829788227