1. Basic processing.
Ensure the floor is free of oil stains and loose particles, smooth, and compact. If possible, use a dedicated grinder to sand the entire floor, followed by removing any loose mortar and debris.
2. Priming Coating Application.
Apply an epoxy primer by rolling or brushing to enhance ground adhesion and sealing. The primer must dry before proceeding to the next step.
3. Mortar layer construction.
After the primer has dried, apply the quartz sand-filled epoxy intermediate coating evenly to the ground using a spatula to fill in holes and cracks, enhancing the ground's flatness and its resistance to heavy loads and impacts.
4. Joint compound application.
Apply epoxy putty to fill in ground holes and defects, creating a smoother and flatter surface.
5. Surface Paint Coating Application.
Apply the epoxy self-leveling flat paint evenly by rolling or troweling to achieve a smooth and level surface. Ensure the coating is uniform with no drips or pinholes.
6. Maintenance.
Once the primer is fully dried, it should be maintained to ensure the floor remains clean, free from heavy impacts and chemical侵蚀.
7. Maintenance and Acceptance.
Upon completion of the maintenance period, the ground is inspected for quality, including luster and adhesion, to ensure the construction meets the required standards.