Sinoyi Group (Glass) Co., Ltd. is a major glass production enterprise. This project is divided into two phases with an investment of approximately 3 billion yuan. Located in the Tieshan Harbor Area, Beihai City, Guangxi Province, it covers over 2,000 acres. Commissioned by them, our company is responsible for constructing the foundation work for this project.

4.2.1 Reinforcement Point Layout Plan

Drive home the point 6.0×6.0m 梅花pattern arrangement, compaction energy of 3000 kN·mThe tamper and lift height should be determined based on the compaction energy. The successful consolidation depth is 6.0 meters.

(1) The ramming point positions can be arranged in a plum blossom pattern, with a 6m x 6m plum blossom layout; count the ramming points once, with an interval of 6 meters; the second round of ramming points should be at the center of the square.

(2) Compaction Pounding: 2 passes, each compaction point to be temporarily pounded 4-6 times; the standard for lifting the hammer: the average settlement of the last two pounding points should not exceed 100mm.

(3) Full compaction passes: 1 pass; full compaction impact energy: 1000 KN.m; full compaction overlap: 1/3.Compaction Testing
During the preliminary stage, the company's chairman personally took charge of organizing the project's commencement, and the client's representative highly praised our preparation for construction.