Section 2: Power-On Preparation
1. Verify gas pressure meets specifications
2. Ensure sufficient cooling water
3. Apply grease to all bearings
4. Check quench and return liquid level
5. Verify the status of all pipelines
Section 3: Furnace Operation Process
**Section 1: Main Furnace Operation**
1. Open the main cooling water valve and adjust the flow rate, ensuring all water lines are clear.
2. Start the conveyor drive motor and calibrate the belt position
Start Mixers Fans 1-4