1. The new external suspension system requires no wall penetration installation, thus preventing damage to the concrete beam and slab structure, and eliminating water leakage.
2. W-beam material consumption reduced; average usage of 1.5 meters is sufficient, lowering procurement costs.
3. All materials except for the plastic pre-buried components are reusable.
Usage Instructions:
After the floor concrete pouring is completed, wait for 18 hours after the floor concrete pouring (adjustable according to the temperature), install the I-beam with steel plate on one side at the pre-buried pipe location on the floor, pass M20#10.9 grade high-strength bolts through the holes in the I-beam steel plate and the pre-buried steel sleeve, add a 80mm×80mm×8mm steel plate on the back with flat washers, spring washers, and nuts tightened.
On the exterior wall, outer beam, and corresponding location of the I-beam on the level above the cantilever floor, pre-bury a steel sleeve (the same as the pre-burial method for the I-beam sleeve). After the concrete on the upper level is poured, begin to install the steel tie rod, which is divided into two sections. One with a rectangular steel plate is installed on the upper floor edge beam, and one with a rounded steel plate is installed on the I-beam吊耳 plate. All connection points are connected with M20#10.9 grade high-strength bolts; then, tighten the turnbuckle bolts to form a triangular force system.
How to use the new cantilever bracket?
1. Determine the location for pre-buried plastic inserts and installation bolts.
2. After demolding, remove the installation bolts and O-rings, and install double-ended high-strength bolts.
3. Place the I-beam in position and secure it with nuts.
4. Erect steel pipe scaffolding;
5. The same method is used to pre-install bolts during the formwork support for upper beam plates.
6. Assemble the pull rod after demolding, adjust to the proper length and secure with a pivot pin.
What services can be provided by purchasing the new suspended scaffold?
1. A professional team offers you free technical guidance
2. Multiple professional exterior frame engineers provide free technical guidance throughout the process
3. Available for steel layout drawings and calculation sheets
4. On-site installation guidance by professional technical personnel

































