Drag reducing agentInstallation instructions:
1Dig trenches according to the design length and orientation on the design drawings: depth0.8-1.0mThe size of the horizontal grounding body wrapped with drag reducing agent is generally150-200*100-150;
2Place the horizontal grounding body (flat steel or round steel, etc.) into the trench, weld it according to the design requirements, and perform anti-corrosion treatment after welding;
3Support the horizontal grounding body with a support to facilitate the wrapping of the slurry;
4.Press the drag reducer and water together2:1Mix the mixture evenly in a bucket truck or other container to form a slurry, then pour it evenly into the trench and wrap it around the horizontal grounding body. The thickness of the coating should not be less than30mm;
5.After the initial solidification of the slurry, backfill the fine soil layer and compact it;
6.Backfill the original soil layer and compact it;
7.Regarding the lead out line, the part leading out to the ground should be wrapped with a resistance reducing agent as much as possible (at least at the end close to the ground grid)50mmThe long part is buried in the drag reducing agent.
Recommended dosage:Burial of horizontal grounding body: trench width0.25~0.3m, deep0.8~1.0mThe filling cross-section of the drag reducing agent is wide0.15~0.2m, thick0.1~0.15mThe dosage is20~30kg/m。