Construction Steps
1. New concrete work that has been leveled and finished with a trowel, to be constructed after curing for 5-7 days.
2. The old concrete surface must be clean, free of oil stains, old paint, etc.
3. Apply Concrete Sealer A, ensuring it is soaked for over 4 hours.
4. Remove excess concrete sealant A, allow to dry.
5. After the ground dries, apply the concrete sealant B, allowing it to soak for over 4 hours.
6. During the soaking process, if the concrete sealer B becomes thick, sprinkle a small amount of water to dilute it.
7. Use a water scraper to remove excess concrete sealant B, then rinse the floor with clean water and dry it with a scraper.
8. Once the surface is completely dry, perform a moderate polishing to achieve a certain level of luster.