EPDM flooring is made by laying EPDM particles, namely EPDM rubber, which is a ternary copolymer of ethylene, propylene, and non conjugated dienes.
1. Asphalt concrete or cement concrete can be used for foundation paving, and it is required to have a certain strength and stability (cement concrete foundation needs to cut expansion joints, and a waterproof layer can be omitted).
2. Cracks and uneven frost heave caused by freezing are strictly prohibited in the foundation.
3. The foundation must have good flatness and specified slope.
4. The surface must be flat and ensure drainage.
5. The basic surface should be kept clean and dry. After the foundation is completed, a strict maintenance period of more than 21 days is required
Construction (manual): After mixing the materials in proportion, pour them into the site and spread them. Use a heated (blowtorch heated) or soap dipped clapper to compact and flatten the joints, maintaining overall flatness.
7. The thickness requirement for the site is generally divided into two stages of construction, taking 13mm as an example: generally, the bottom layer is made of 8mm rubber particles and the surface layer is made of 5mm EPDM particles.