Cold storage design specifications enter the construction site. According to the construction drawings, verify the construction status, and determine the equipment installation locations (including the storage body, drainage door, evaporator, main unit, condenser, control system, etc.).
Installation Method for Cold Storage Panels
Floor Installation
1.1 First, level the ground surface, then begin the installation of the flooring. Choose aesthetically pleasing flooring for prominent areas and ensure proper drainage systems for the flooring and evaporator.
1.2 Quality Requirements
The floor is installed level, with uneven areas leveled using materials. The locking hooks between the boards are then secured to achieve a smooth surface with no hollow feeling. (Note: For this drainage system, if the cold storage body is installed outdoors in the north, the drainage pipes need to be insulated.)