Soil mold spinning cutting pile cap cast-in-place construction method
2025-02-27

Process Features
Streamlined process, high efficiency, and rapid speed.
The soil mold method, utilizing mechanical filling followed by manual excavation, eliminates the need for soil excavation and backfilling between CFG piles after pile formation, streamlining the work process and enhancing construction speed; the use of our self-developed spiral cutting pile saw to cut off pile heads reduces the labor intensity for workers, significantly improving work efficiency.
2. User-friendly, low disturbance, high quality.
The soil mold method can prevent excessive disturbance to the soil between piles below the design level of the pile cap due to the removal of protective soil layers and the removal of pile heads, thus solving the issues of broken piles and poor quality of soil backfill caused by mechanical excavation operations. The idea of the rotary cutting pile cutting mechanism is innovative, allowing for convenient operations within the narrow soil mold space. It can address the challenges of not being able to operate a conventional pile cutting machine inside the soil mold and the problems associated with using jackhammers to remove pile heads, such as time-consuming and labor-intensive work, poor appearance, and a higher risk of damaging the pile.
3. Advanced technology, easy construction, and convenient promotion. The site hardening, pile cap soil mold excavation, and saw cutting桩桩 construction techniques are easy to master, with the construction organization elements configuration readily achievable, which is conducive to promotion.
4. The equipment is ingeniously designed, cost-effective, and yields significant benefits. Our independently developed桩截断机构 features exquisite design, simple structure, easily accessible parts, and low manufacturing costs, allowing for self-processing. This effectively reduces the investment in equipment costs, leading to significant social and economic benefits.
Above is the introduction to the construction method of soil mold spiral cutting桩cap cast-in pile construction. If there is anything else you are unclear about, feel free to consult our website, where we have professionals to explain it to you.
王华伟 (Mr.)
18753770336
18753770336
609018831@qq.com
105 National Highway & Rencheng Avenue intersection, 80 meters west along the north road, West Building, Room 12, Yongfeng Logistics Compound
b2b.china9.net © Zhongshang 114 Hebei Network Technology Co., Ltd.Address: Room 6009, Oriental New World Center, No.118 East Zhongshan Road, Qiaoxi District, Shijiazhuang City, Hebei ProvincePlatform Service Hotline: 4006299930