Equipment used across different industries varies greatly. The textile industry typically employs machines such as folder machines, pleater machines, and pleating machines, among others. The expansion machine is a commonly used piece of equipment in engineering. Below, we'll explore the installation steps for the expansion machine, which we have divided into eight aspects for easy understanding.
One, Foundation Requirements: The concrete foundation must be poured with a thickness exceeding 100mm; the concrete surface should be ensured to be smooth.
Secondly, reassemble the two main parts, the brackets and the extensions, which were previously disassembled, at the installation location, and secure the other installation screws.
If online production, the machine's central axis should align with the production line's axis during installation, and the center height adjustment should be made.
Four: Perform horizontal alignment of the machine in both forward-backward and left-right directions.
Fill the fuel tank with 160 liters of pure YA-N46 hydraulic oil, ensuring the oil remains clean and free of impurities. When refueling, use a filter device to inject the oil.
All lifting screws, guide columns, guide rods, chains, and chain wheels should be lubricated with an appropriate amount of grease.
Seven: Connect power and control lines according to the circuit diagram.
Section 8: Install water supply, drainage main, and flexible hoses connecting to the machinery according to the waterway map.
The installation steps for the expanding mouth machine have been covered. We hope this has been helpful. Should you have any further questions, please continue to follow our company website, where we will be more than happy to assist you. Of course, we will also introduce knowledge on other aspects in the future. If interested, you can also look up information online, as there is quite a bit of information available on the web regarding this topic.