Hubei Suizhou PE Water Tank, Sewage Treatment Storage Vessel, 30 Cubic Meter PAC Mixing Drum, Acid and Alkali Resistant Plastic Water Tank_SupplyPro Co., Ltd._Hubei Jingxing Plastic Products Co., Ltd.
Hubei Jingxing Plastic Products Co., Ltd.

Specializing in the production of PE water tanks, water towers, storage tanks...

Soule Star Diamond Member
Sales Hotline:
13545006024

Hubei Suizhou PE Water Tank, Sewage Treatment Storage Vessel, 30 Cubic Meter PAC Mixing Drum, Acid and Alkali Resistant Plastic Water Tank

产品Price13800.00/Piece

最小起订Quantity:1 Piece 可售数Quantity:200 Piece

有效期至:
长期有效
最后更新:
2025-10-11 15:58


Product Details

Here are the detailed installation steps and precautions:

Preparation before Installation

1. Basic Construction

Basic Requirements:

Material: Concrete (C25 and above), surface treated for corrosion resistance (e.g., epoxy resin coating or asphalt corrosion protection).

Size: Diameter ≥ Tank Diameter + 0.5m, Thickness ≥ 20cm (to be calculated by structural engineer for load-bearing capacity).

Flatness: Horizontal error ≤ 3mm/m², to prevent uneven stress and deformation of the storage tank.

Drainage Design: Basic perimeter drainage channels are installed to prevent water accumulation and corrosion.

Silt Barrier (optional):

Volume ≥ 110% of the total tank capacity (i.e., ≥ 55 m3), to prevent leakage and environmental pollution.

2. Tank Acceptance

Inspection Items:

No cracks, scratches, or deformation on the appearance.

Flanges and interfaces are undamaged, with intact sealing washers.

Enclosed documents (Certificate of Compliance, Material Report, Pressure Test Report).

3. Tools and Personnel Preparation

Tools: Crane (over 10 tons), nylon slings (anti-scratch), level, wrench, PE welding gun (for on-site welding if required).

Personnel: At least 2 installers + 1 technical supervisor

Section 2: Tank Installation Steps

1. Hoisting into place

Lifting Method:

Use nylon slings (prohibit direct contact with the tank body with wire rope to avoid scratching).

Select lifting points at the tank's dedicated lifting lugs or reinforced rib locations; direct lifting of flanges or pipes is strictly prohibited.

Slowly hoist, after lifting off the ground, hover to check for balance, ensure no tilt.

Placement Adjustment:

Tank bottom lined with rubber pads or PE boards (anti-slip, anti-corrosion).

Adjust with a level to ensure overall levelness (error ≤ 5mm).

2. Pipe and Fitting Connections

Inlet/Outlet Tube:

Use PP/PE/PVDF material piping to prevent metal corrosion.

Flanged connections use EPDM or PTFE gaskets, and bolts must be treated for corrosion resistance (e.g., plastic coated).

Recommend installing acid-resistant valves (such as PTFE-lined ball valves) at the discharge outlet, and setting up a filter (to prevent crystalline blockage).

Exhaust and Safety Equipment:

Breathing valve installed at the top (to prevent vacuum or overpressure).

Level gauges are selected to be magnetic flip or radar type (to avoid metal contact with the solution).

3. Mounting and Reinforcement

Wind and earthquake resistance

Steel clamps (304 stainless steel or carbon steel with anti-corrosion coating) are added around the tank perimeter and secured to the concrete foundation.

Areas in seismic zones require additional anchoring bolts for stabilization.

Ultraviolet Protection (PE/PP Tanks):

Outer surface wrapped with aluminum foil tape or coated with UV-resistant paint (extends lifespan).

3. Post-installation Inspection and Testing

1. Sealing Integrity Test

Water Pressure Test:

Fill with water, let stand for 24 hours, and check for any leaks in the container and joints.

Check for bubbles at the flange connection with soap and water.

2. System trial operation

Add Liquid

First, inject a small amount of solution (10% to 20% capacity), and then operate at full load after observing for 24 hours without any abnormalities.

Inspect the level gauge, valves, pumps, and other auxiliary equipment for proper operation.

Section 4: Safety and Maintenance Precautions

1. Safety Protection

Corrosion resistance:

Operators wear acid-resistant gloves and protective goggles.

Flush with large amounts of water in case of leakage (the corrosiveness of FeCl? can be reduced by dilution with water).

Fire and explosion proof

Keep away from heat sources. Welding operations are prohibited near the storage tanks (HCl gas is flammable).

2. Routine Maintenance

Monthly Inspection:

Dome for expansion and cracks (especially in winter at low temperatures).

Are the flange gaskets worn out, and are the bolts loose?

Annual comprehensive inspection:

Thick Wall Measurement (Ultrasonic Inspection), to prevent long-term corrosion thinning.

Section 5: Comparison of 50m3 Storage Tank Installation Solutions

HDPE Rotomolded Storage Tanks, Steel Lined Plastic Tanks, FRP Storage Tanks

Low installation difficulty (overall hoisting), medium (requires lining welding), high (requires construction)

Corrosion resistance: Good (seam prone to leakage), Excellent (without seam), Excellent (requires resin matching)

Low Cost (30,000-60,000 RMB), Medium Cost (80,000-120,000 RMB), High Cost (150,000-200,000 RMB)

Recommended scenarios: room temperature, low concentration (<30%), pressure-bearing; high concentration required for high temperature; special corrosive environment.

Summary

Installation of 50m3 storage tanks requires particular attention to foundation flatness, lifting safety, pipeline anticorrosion, and sealing integrity testing. HDPE rotational molding tanks are cost-effective and durable, but for high concentration or high-temperature conditions, steel-lined or glass-fiber reinforced plastic should be chosen. Regular maintenance can extend the tank's lifespan to over 10 years.

询价单
主题 *
内容 *
Your company's名
Contact person *
ContactPhone *
电子Email
验证码  
 点击确定代表您同意《服务条款》《隐私政策》
 

Phone Consultation

Consultation Phone:

WeChat Service

Add WeChat

Back to Top

 Click submit means you agree to《Service terms》《Privacy policy》