The large clock face is made of aluminum plate with electrostatic spraying, never rusts, and maintains its color for 30 years outdoors. The clock hands are laser cut from stainless steel and then coated with paint. The control system features a modular design, ensuring stability and reliability. The movement operates intermittently, is environmentally friendly and energy-efficient, fully enclosed, and requires no maintenance, with a design life of up to 50 years.
Tower Clock Grand Clock Production and Installation Process
Estimated Completion Time: [number] calendar days
Including: Manufacturing Lead Time: 20 days
Transportation and installation timeline: 10 days
I. Production, guaranteed manufacturing timeline plan
1. Based on the signed contract. The day after the contract is signed, the company will issue production schedules to all production departments (individual production workshops, R&D department, logistics center). The schedule will specify details such as the size, color, features, and shipping time for each piece. A detailed "Material Requirement Sheet" will also be attached.
2. The technical department is responsible for determining the technical solution based on the specific requirements of the bid document from Party A, and providing it to the production workshop for production. The logistics center, based on the "Material Requirement Sheet" and the current inventory, drafts a detailed "Procurement Plan." The procurement plan is issued to: electronic component procurement specialist, outsourced procurement specialist, and bulk material procurement specialist. Additionally, the approximate required funds are notified to the finance department.
3. Begin procuring various materials starting from the second day, with a priority on acquiring urgently needed supplies for production.
4. The company's existing stock of materials and spare parts, such as control systems and cores, will be immediately put into production as per the contract requirements. The basic manufacturing of control systems and cores will be completed within the 3rd to 13th day. They will then progressively move into the debugging and trial operation processes.
5. The clock face production should be basically completed between the 3rd and 13th day (the exterior parts do not require adjustment).
6. By the 8th to 11th day, all packaging materials will be in place, and the wooden boxes for packaging will be completed.
7. All debugging completed within the 18th day, perform inspections prior to packaging, and fill out various documentation and forms for packaging.
8. All packaging is completed by the 19th day.
9. Notify Party A that the shipment is ready for dispatch and confirm with Party A the specific unloading location and installation time.
10. The installation personnel will arrive at the installation site ahead of the agreed time by both parties to prepare for the installation. The following day, they will inspect the goods together with Party A and begin the installation.
Section 2: Clock Equipment Transportation and Installation Plan:
(Part 1) Packaging, Shipment, and Transportation Solutions
1. For packaging, general control instruments and computer accessories are packed in cardboard boxes, with shockproof foam and moisture-proof plastic bags inside. For clock faces, valuable items (such as control boxes, clock hands, and dials), and items weighing over 20 kg, an additional wooden crate (made of high-quality plywood) is placed over the cardboard box. Shockproof foam is also added between the wooden and cardboard boxes. All packaging is neat, aesthetically pleasing, and reliable, loaded onto trucks according to road transportation requirements to ensure the items arrive at the destination intact.
Each carton contains a detailed product packing list, factory inspection certificate, quality inspection certificate, and manual, etc. The carton is sealed after being inspected and approved by the inspector.
Each package box is imprinted with the shipper, departure station, consignee, destination station, product name, gross/net weight, total number of packages in this shipment, contract number, etc. Additionally, it features the "Three Protection" symbol.
4. Transportation. For this *** equipment, our company will select the most suitable transportation method, such as road or rail, based on the installation location of the tower clock project and the requirements for equipment transportation security. We guarantee the safe, accurate, and timely delivery of the goods to the destination. Any losses caused by loss or damage will be borne by our company. Within 48 hours prior to the shipment of the equipment, we will send the recipient a fax with details including the station name, quantity, estimated installation date, contract number, material name, quantity, gross weight, volume, amount, name of the transportation vehicle, and the equipment shipment schedule.
5. Arrival Inspection and Handover
Upon arrival at the buyer's destination, our project manager and the buyer's representative will jointly inspect the goods in accordance with the contract. The inspection scope includes the quantity, specifications, model, quality, and performance parameters of the equipment. Both parties will sign and seal the delivery (receipt) document, which serves as a crucial basis for operational handover. If any goods do not meet the buyer's requirements, the buyer has the right to refuse acceptance or request a replacement, and any resulting costs will be borne by our company.
(II) On-site Inspection and Entry for Installation
1. On-site Installation Inspection
1) Upon arrival of the goods on-site, the installation personnel will inspect the quantity of packaging boxes and their condition for any damage or missing items, in accordance with the "Shipment Registration Form," together with the recipient.
2) Inspect the goods inside the packaging boxes with the buyer, and check off each item as listed on the packing list.
3) Briefly describe the names, quantities, uses, and storage requirements of various goods to facilitate the provider in securing a safe storage location.
2. Installation On-Site
1) All goods will enter the site according to the installation time as per the contract or agreed upon by both parties. Prior to installation, the storage location for the goods will be agreed upon with Party A, ensuring a safe place for the uninstalled goods.
2) Collaborate with the buyer to establish installation conditions and make modifications to any conditions that do not meet requirements, ensuring a safe and smooth installation.
3) Inform the buyer of the approximate time for acceptance to allow preparation.
(3) Clock Equipment Installation
Equipment Installation Steps:
Assemble the clock face on the designated work surface.
2. Rent suitable hoisting equipment and employ the whole-set hoisting method to weld or bolt the large bell steel frame to the reserved ironwork in the bell tower.
3. Reserve pipelines between the subclock and the master clock, lighting lines, and pipelines between the horn and the amplifier.
4. Accept scale lighting wire, movement lighting wire.
5. Install the speakers and connect the speaker power cables.
6. Connect the motor wire and feedback wire to the motor and feedback switch on the core.
7. Connect all motor lines, feedback lines, lighting lines, and speaker lines to the master clock system and the amplifier's control room.
8. Connect to the GPS time synchronization system.
9. Connect and debug the monitoring microcomputer.
Section 3: Clock Equipment Operation and Adjustment
Debugging period: 3 calendar days; simultaneous on-site training for the client's designated operators will be conducted during the debugging phase.
On-site Installation: