In recent years, porcelain steel plates have been extensively used in the engineering field of environmental-friendly biogas projects, specifically in steel-made HAIYUE CSTR.Anaerobic Assembly TankOur UASB fermenters employ different fermentation processes, yet both these enamel-lined modular tanks are installed on concrete foundations. Today, Haiyue...Assembly罐The company shares with you the installation considerations for UASB enamel fermentation tanks and the construction standards for biogas CSTR assembly tanks.

What to Pay Attention to When Installing Haiyue Enamel UASB Fermentation Tanks:
Firstly, inspect the strength of the deformable steel components and aspects such as the wall panels and filling columns of the glass-lined UASB fermenter to ensure its stability. Reinforcement treatments can be conducted if necessary. During installation and alignment, consider the factors of deformation caused by glass-lined steel plate welding and make reasonable adjustments.The design of the fermentation tank requires that pipe fittings be tightly sealed with a sealing surface larger than the contact area. The drainage pipes, feed/unfeed pipes, detection in/out pipes, sampling tubes, and ventilation pipes installed on the tank must be strictly installed according to the design standards. When other components and equipment are suspended from the installed structure, checks, calculations, and corresponding safety protection procedures should be carried out.
Haiyue Biogas CSTR Assembly Tank Installation Component Construction Standards:
The anaerobic tank assembly height is permitted to vary ±2 cm, with a verticality of 1/1000. The external deviation of the top of the sea tank assembly should not exceed 3 cm. The height of the upper and lower inspection holes should not exceed 2 cm. The height deviation between the in/out water pipes, sludge discharge pipes, detection holes, sampling tubes, and ventilation pipes should be ±1 cm, and the horizontal displacement should not exceed 2 cm. Check for kerosene leaks at the entire welded area of the steel anaerobic tank. The installation of other components and facilities should be based on the relevant design drawings for the assembled tank. The installed CSTR anaerobic tank assembly and UASBFermentation Assembly VesselInternally and externally, rust and corrosion prevention treatment as well as tank sealing performance tests should be conducted uniformly.